Hang 45deg woody off engineered i joists?
|
I'm building a woody in the basement and am looking for advice. The floor joists above are engineered I joists. The wall will be 10' wide, 10' long, 45 degrees. It will run perpendicular to the joists so I could attach the header to 6 joists. I've read a lot of conflicting info online as to whether or not: |
|
I cut 2x10 to fit tightly between the joists and screwed them in from the sides. Placed them in every other gap, then bolted a 2x10 the length of my wall to them as a header. Seems pretty stable and I’m a pretty big guy. |
|
My main woody is 43 degrees and 20' wide, and I hung it directly from Engineered joists; no header. |
|
Awesome, thanks for the replies, gents. Much appreciated. |
|
It’s best to screw into the face (bottom) of the TJI, it has better holding strength then screwing into the sides. Use a 2x12 header with 3 #10x3” screws per joist and you will be fine. |
|
I used a 2x8 header on mine with 4 deck screws into the bottom of each beam. I also went into the top plates of the adjoining walls on each side. That being said, I do tend to over engineer things. |
|
Kevin Stricker wrote: It’s best to screw into the face (bottom) of the TJI, it has better holding strength then screwing into the sides. Use a 2x12 header with 3 #10x3” screws per joist and you will be fine. Hi Kevin, I would normally agree but if you screw into the sides of BOTH rails (top and bottom), I think it's stronger than just screwing into the bottom. It creates a very strong box-triangle structure which distributes the forces. And adds a few more moves per problem. I will emphasize that properly sized pilot holes are important for the TJI so you don't damage the laminate. |
|
Mike, |
|
Just to put this out for anyone lurking, engineered joists have very strict limitations on putting holes through the middle matrix, and by no means should you ever consider cutting one of the top or bottom cords |
|
Crossing wrote: Mike, Mike, Standard practice in this case is to use 2x4 sleepers across 3-4 joists every 4’. In this way you can distribute the load over more joists. It’s also important to consider that even a 45 degree wall will have a large shear component to the load. It is not a direct downward load, and at least 1/2 of the dead load is being transferred to the wall below.John, incorporating the upper chord can add to the allowable load but it does compromise the strength of the TJI. Your screws are stronger in shear than pull-out but the endgrain of the plywood caps have much lower strength. Can’t argue with the extra wall space though and if your joists are running full height it’s sure to be a bomber connection once the plywood is installed. |
|
Kevin Stricker wrote: John, incorporating the upper chord can add to the allowable load but it does compromise the strength of the TJI. Your screws are stronger in shear than pull-out but the endgrain of the plywood caps have much lower strength. Can’t argue with the extra wall space though and if your joists are running full height it’s sure to be a bomber connection once the plywood is installed. Yes, thanks. I don't remember the exact sizes, but... the pilot holes are sized so that the screw lags (pulls tight) the 2x6 without "exploding" the laminate. I would drill a pilot hole through the laminate and into the 2x6, then using a slightly larger size, re-drill the hole just through the laminate. It's quite strong this way. Also, the plywood is attached to every joist along the top edge. |
|
Thanks again for the help! John - I really like your idea of running the frame of the climbing wall up to the top flange of the i-joists, both to maximize climbing height and also increase the strength by including the top flange of the i-joist. If I do this I'll get nearly 9' of vertical height which would be rad. |
|
mbb wrote: Thanks again for the help! John - I really like your idea of running the frame of the climbing wall up to the top flange of the i-joists, both to maximize climbing height and also increase the strength by including the top flange of the i-joist. If I do this I'll get nearly 9' of vertical height which would be rad. I just used heavy gauge "drywall" screws. Yes, you have to screw into the sides, but with a properly chosen pilot hole diameter, you won't split the laminate. Use screws that have a smooth shaft near the head (no threads) so they lag. (see above) I don't think I damaged the laminate at all. Oh, I didn't center the screws in the flange, but put it two-thirds up from the bottom. You might get some scrap and experiment. If you're still worried, cut a triangular piece (3ft on short edges) of plywood and mount it behind the wall. One edge to the wall-joists (2x6) and the other along the TJI's to distribute the load. As I said, my TJI's are on 12" centers, rather close, YMMV.Oh, you can "get away" with a 12" kick panel, instead of 18", at the bottom to maximize your overhanging area. |
|
mbb wrote: Thanks again for the help! John - I really like your idea of running the frame of the climbing wall up to the top flange of the i-joists, both to maximize climbing height and also increase the strength by including the top flange of the i-joist. If I do this I'll get nearly 9' of vertical height which would be rad. Mike, As Kevin mentioned above, I would not recommend fastening to the side of the flanges. It's a weak connection and risks compromising your floor. See Trus Joist bulletin TB-206 here to see that the largest fastener they recommend into the side of a flange is 0.148" diameter. That's about the same as a #9 or #10 screw. And the minimum spacing is 6" o.c. They also don't provide a value for that connection. Technical bulletin TB-203 (here) gives guidance on hanging sprinkler systems from TJI joists, and it says "Connections into the side of TJI joist flanges are not recommended". They provide a design for connecting to the bottom of the flange.Kevin gave you a good connection into the bottom of the bottom flange: (3) #10x3" screws. Run a 2x12 header along the bottom of all the joists with that connection at each joist. Then hang your studs from that header. Don't use drywall screws - get the good ones. I like the GRK screws, which I think Home Depot is carrying now. You can still extend the plywood up between the joists. If you have a full sheet of plywood that is mostly secured to the main wall framing below, and notched to extend up into the joist bays, then the load to any blocking you have up in the joist bays will be minimal. I'd probably just put some 2x4 blocking between the webs of the joists to connect the plywood extensions to. You can nail or screw this blocking in place from the other side of the web. If there is already blocking in that bay, just angle the connectors a little. This blocking will not be doing much work. |
|
Another carpenter/construction guy here basically confirming that all points that Rich said above are 100% spot-on, including choice of fasteners. In this application the choice of fasteners matters somewhat. |
|
Okay, so I did it wrong. I'm not too worried as the wall has been there and used for 8 or 9 years, and there are no creaks, cracks, movement or other indications of weakness. However, since some of you seem to know what you're doing, can you answer some questions? I've looked through the links and can't find a relevant section that talks about a similar installation. |
|
John, |
|
Awesome, thanks all! I mounted the header to the bottom flange as per recommendations above and the tech docs. Header runs across 6 joists and seems mega solid. Wall ended up being 35 degrees, better compromise between my training wants and what the kids will be able to climb on. For now I'm not extending the wall above the bottom of the joists but good to know this is still an option with a bit of blocking up higher attached to the web. |
|
The easy answer is that TJI's are designed to carry loads a certain way and along a certain axis, and they are more susceptible to 1) problems associated with delamination and 2) secondary stress forces (such as moment stress which is basically "potato chipping") than wood joists. Carpenters add secondary blocking when necessary in floor construction to mitigate these forces. These applications are always intended to deal with loads from above, obviously. |
|
mbb, I use door hinge halves as my dry tool holds. Works great! |